
 |
|
UPDATING NEWS |
|
Method of Moments array design and proofing approved by the FCC.
AGSC begins MoM proof retrofit preparations for stations.
Story |
|
Law Enforcement Officials overjoyed that Heroin use is
increasing... Story |
|
New State laws aimed at curbing copper theft seem to be working.
Story |
 |
|
|
2010
|
|
WQEW |
New York, NY |
|
August 2010
Repair original ground system where builder
used incorrect brazing alloy, install ATU arc gaps and other repair
work. |
|
KILT |
Houston, TX |
|
January & August 2010
MoM Preparation. Install new sample
lines, fences and other grounding |
|
KIKK |
Houston, TX |
|
August 2010
Install fence grounding |
|
WAGG |
Birmingham, AL |
|
May 2010
Repair ground system damage caused by
construction around towers. |
|
WIOZ |
Aberdeen, NC |
|
March 2010
Evaluate vandalism to ground system and feed
system. |
|
KWAM |
Memphis, TN |
|
July 2010
Locate and mark ground system and feed lines
for future site construction. |
|
|
|
|
|
|
|
|
2009
|
|
WRLM |
Irondale, AL |
|
Janurary 2009
Install new ND ground system |
|
KELP |
El Paso, TX |
|
March 2009
Rebuild 3 tower ground system following
construction damage |
|
WQXI |
Atlanta, GA |
|
December 2008
Rebuild 2 tower DA ground system and other
grounding work |
|
WBCO |
Bucyrus, OH |
|
August 2008
Install new sample line via Directional Boring |
|
WABC. |
New York, NY |
|
July 2008
Ground System Evaluation and Repair |
|
KRVN |
Holdredge, NE |
|
July 2007
Ground System Evaluation |
|
WBWL |
Jacksonville, FL |
|
June 2008
Rebuild 5 tower Inline DA |
|
KWAM |
West Memphis, AR |
|
Feburary 2008 and beyond
Refurbish array infrastructure, site
access, array tuneup |
|
XEGH |
Rio Bravo, Mexico |
|
November 2007
Build new ground system |
|
KTIS |
Minneapolis, MN |
|
October 2007
Evaluate and repair ground system |
|
WILC |
Laurel, MD |
|
July 2007
Repair and enhance tower base
grounding |
|
KDWA |
Hastings, MN |
|
July 2007
Build new ground system |
|
WIBC |
Indianapolis IN |
|
July 2007
Repair and enhance tower base
grounding |
|
WNOG |
Naples FL |
|
June 2007
Ground System Evaluation |
|
WYHL |
Meridian
MS |
|
June 2007
Rebuild ND Ground System |
|
KZDC |
San
Antonio TX |
|
March 2007
Build New 4 tower ground system |
|
WCIN |
Cincinnati
OH |
|
June 2007
Repair vandalism damage. |
|
WMBG |
Williamsburg
VA |
|
March 2007
Build New ND ground system |
|
KCRG Cedar
Rapids, IA
October 2006
Rebuild 3 tower ground system and
install new feed and sample lines. |
|
KRLD
Dallas TX
December 2006
Rebuild 2 tower array ground system
and building ground infrastructure. |
|
WPHE
Phoenixville, PA
September 2006
2 tower DA rebuild |
|
KDWA
Hastings, MN
July 2006 ND Build |
|
WCIN
Cincinnati, OH
Feb. 2006 5 twr DA Build |
|
WNDA Deland, FL
Dec. 2005 ND Rebuild |
|
KMOX
St. Louis, Mo
Nov. 2005
ND Rebuild & other work. |
|
|
| |
|
|
| |
|
|
| |
|
|
| |
This Page has had |
|
| |
 |
|
| |
Visitors Since The Site was Rebuilt
September '05 |
|
| |
|
|
|

Winter is Coming again this year.
Duh...
Every year we get at least one call
in October wanting to know how quick we can build a ground system.
My standard answer is, "It will take about a week start to finish
for a single tower and probably less than 2 weeks for multi-tower
arrays".
The caller meant but didn't state;
"It is 33 degrees here today. Even though I have had my CP for
two and a half years, I have waited until the forecast is calling
for a FREEZE warning and I still haven't gotten my station built.
AND the CP runs out in January. How QUICKLY can
you drop everything and get my station built before winter?"
Winter work in general costs more
than fair weather work. Equipment preparations, clothing
requirements, speed of work, length of work day, weather delays ALL
cause winter weather work to be more expensive than summer work.
Not to mention the impact on safety. Restricted vision,
dexterity and movement are serious concerns when working on and
around heavy equipment.

As anyone involved in building
broadcast stations is aware, more government agencies have their
fingers stuck in the radio business more than maybe even the Nuclear
Power industry (I could be mistaken on this). Three years can
barely be enough time by the time all of the acronym's are
satisfied.
HOWEVER, most of the
rush-before-winter projects that we do are for one of 2 reasons:
-
Procrastination
I'll get that done tomorrow! Or
the next day! Maybe... If I get to it... Oh... Hey!
Its October... Again.
More time and money is wasted on
site construction because of procrastination than any other
preventable cause. RUSH costs money. Getting
materials in a hurry costs more, travel costs more, guaranteeing
delivery of other materials and services cost more, etc, etc.
-
Saving Money
I have provided proposals to stations
that have point-blank told me that I was too expensive. They
hunted around and found someone that said that they could do the
work for a small percentage of my proposal (see
my treatment of the exceeding cheap quote). And then they never
show up. On one memorable project, it cost the client almost
50% more than my original proposal from a year earlier.
Materials and mobilization were up due to availability and market
factors. Shipping was astronomical due to speed, weight and
location factors. Mobilization was driven up by lack of
advance purchase time. Rush costs money. Extra labor was
required to finish by the CP expiration.
I have also had a RUSH client tell me
that they would have called AGSC to start with but had been
convinced by someone that they could do the job cheaper than anyone
around. They were absolutely correct. The work was never
done, henceforth, it cost the station NOTHING! Until we/they
had to pay expedited shipping charges and shuffle properly planned
projects around. RUSH costs money.
Regulatory delays comprise a fairly small
portion of our compressed time line work.
When we (Or anyone. Even you.) order
materials and make travel plans on a compressed time line, the costs
will be higher. Every facet of the project will usually be
impacted when adhering to a compressed time line. The more
compressed, the more expensive. Rush costs money.

We Specialize in
Compressed
Time Line Projects
We have the resources, equipment and
knowledge to make a project "happen" just in time. By saying that
we specialize in compressed projects doesn't mean that we encourage or
like them. Just that we can "git 'er done" if needed.
Some tips to help make your project go a
little smoother.
-
Choose your venders and contractors
(tower, ground system, building, utilities, equipment, etc) early.
You should already be talking to venders and contractors before
the initial application is filed. Contractors and equipment
should be lined up AS SOON as the CP arrives. Even if the
proposed the construction date is months away.
-
Choose your venders and contractors
wisely. A great deal isn't necessarily a good value.
-
Ask for references. We have a
reference page HERE so you can check us out
-
Regularly follow up on equipment delivery,
construction dates and contractor status.
-
Know EXACTLY what permits and permissions
will be required BEFORE you file your application. Moving to another
site may save a large sum of money if permits or remediation can be avoided.
-
Contractors should be in touch with each other
for coordination. However, SOMEONE (you, your engineer, GC, or even myself
as a site coordinator) MUST be in overall control of the time line AND
scheduling.
-
Return contracts, proposals and payments
according to the vender/contractor requirements. Failure to return a
contract or payment in a timely manner may result in unplanned delays.
-
Go to the doctor. Get something for your
stomach and something for your head. The larger the project the
more/better something you may need. For the humor challenged, this is only
half joking. Especially if you didn't contract AM Ground Systems
Company.
|
|